Selectmen approve multiple change orders for renovation project; OK $3,254.77 reserve fund for fire engine tires

Board of Selectmen · March 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Selectmen approved several PCOs for the fire/highway/building renovation and a reserve fund purchase of $3,254.77 for two wheels/tires for Engine 2; staff said the project remains under budget.

The Board of Selectmen on March 10 approved a package of project change orders for the town’s fire/highway/building renovation and authorized a reserve fund purchase to replace wheels and tires on Engine 2.

Project change orders: Project staff reviewed and the board approved the following PCOs/change-order items: PCO O75 — $854.43 (access panel in a closet to access existing piping); PCO O76 — $568.45 (additional fire stopping per the building inspector); PCO O78 revision 1 — $2,556.74 (sprinkler piping work); PCO O79 — $962.39 (install a photocell to control exterior lighting); PCO O80 — $7,412.04 (new doors and windows at the DPW); and PCO O81 — $1,209.29 (fire alarm monitoring and programming). Speaker 5 clarified on the record that a prior on-camera statement misstated which items related to sprinkler piping versus sheetrock/patching and corrected the record.

Reserve fund for Engine 2: Earlier in the meeting the board approved a reserve funding request for $3,254.77 to buy two wheels and tires for Engine 2 after the vehicle was found to have unsafe, dry-rotted tires. The chair praised the fire department for a “creative way of solving the problem,” noting the purchase was funded from a gift account and a finance committee recommendation.

Budget status: Project staff told the board the overall project remains under budget and that the team did not need to request additional town funding at this time; a final meeting of project stakeholders was scheduled to determine use of any remaining funds.

Provenance: PCO details, clarifications and budget status were discussed during the change-order agenda item and the reserve fund request was handled earlier in the meeting.