County reports 75% completion on Integrated Water Master Plan; contingency partially spent
Summary
Utility staff told commissioners the integrated water master plan is about 75% complete, targeted for delivery mid‑July 2026, and that roughly $272,000 of a $742,000 contingency has been authorized; additional studies (Sebastian septic‑to‑sewer feasibility and a pump‑station conversion) are underway.
Howard Richards, manager of capital projects for the Department of Utility Services, briefed commissioners on the Integrated Water Master Plan, a HDR Engineering project designed to address growth, aging infrastructure and regulatory change over a 20‑year planning horizon.
Richards said the plan will be delivered as modular tasks and that staff have completed the vision and performance…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat