Village awards $596,293 wastewater UV replacement contract, OKs $34,718 engineering agreement

Village of Hampshire Board of Trustees · December 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board awarded the wastewater treatment facility ultraviolet‑system replacement construction contract to Boiler Construction Co. for up to $596,293 and approved a professional services agreement with EEI for construction engineering not to exceed $34,718; staff noted the project must be in place by May 1 to comply with the village’s NPDES permit.

Hampshire trustees on Dec. 5 awarded the construction contract and engineering services for a wastewater treatment facility ultraviolet (UV) system replacement.

Staff said engineers’ opinions had estimated the project at roughly $631,000, but competitive bids returned a low bid of $596,293; the lower bid still comes with a tight schedule, as the replacement must be operational by May 1 to meet NPDES permit requirements. The board awarded the construction contract to Boiler Construction Company in an amount not to exceed $596,293.

The board also approved a professional services agreement with EEI for construction engineering and construction observation services (shop drawing review, pay‑application review, punch‑list, record drawings) in the amount not to exceed $34,718. An EEI representative explained the engineer acts as the owner's representative and may disapprove work not meeting specifications; staff said significant issues would be brought to the village’s attention.

Both measures passed on roll calls of 6‑0.