Village awards $596,293 wastewater UV replacement contract, OKs $34,718 engineering agreement
Summary
The board awarded the wastewater treatment facility ultraviolet‑system replacement construction contract to Boiler Construction Co. for up to $596,293 and approved a professional services agreement with EEI for construction engineering not to exceed $34,718; staff noted the project must be in place by May 1 to comply with the village’s NPDES permit.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Hampshire trustees on Dec. 5 awarded the construction contract and engineering services for a wastewater treatment facility ultraviolet (UV) system replacement.
Staff said engineers’ opinions had estimated the project at roughly $631,000, but competitive bids returned a low bid of $596,293; the lower bid still comes with a tight schedule, as the replacement must be operational by May 1 to meet NPDES permit requirements. The board awarded the construction contract to Boiler Construction Company in an amount not to exceed $596,293.
The board also approved a professional services agreement with EEI for construction engineering and construction observation services (shop drawing review, pay‑application review, punch‑list, record drawings) in the amount not to exceed $34,718. An EEI representative explained the engineer acts as the owner's representative and may disapprove work not meeting specifications; staff said significant issues would be brought to the village’s attention.