Macomb to seek grants and use West Side TIF for Chandler Park design; $194,000 schematic work proposed
Summary
City staff told the Committee of the Whole on Aug. 11 that completing design for Chandler Park is needed to apply for ITEP and OSLAD grants; staff proposed paying approximately $194,000 from the West Side TIF and will place the design contract on the next council agenda.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
City staff told the Macomb Committee of the Whole on Aug. 11 that the Chandler Park master plan is complete and that schematic design must be finished to be competitive for two major grants: an ITEP grant through the Illinois Department of Transportation and an OSLAD grant through the Illinois Department of Natural Resources.
City administrator Scott (surname not provided in the transcript) said the city has money available in the West Side TIF and expects the TIF account to have roughly $400,000 by the end of the fiscal year. He said schematic design for Chandler Park is estimated at about $194,000 and that the full project, when escalated, might reach about $3,600,000.
Scott and other council members emphasized that the master plan’s overall park layout would not change in a major way but that design work is needed for elements such as a performance space and shelters. Alderman Katz said finishing design before submitting grant applications is essential to be competitive.
The committee discussed public outreach and agreed to continue the matter to the next city council meeting so the council can consider authorizing the contract; staff indicated the expense is TIF‑eligible and would be paid from the West Side TIF account.
If approved at the council meeting, staff said the goal would be to complete the design in time to apply for grants next summer.