Hasmer Lake project engineering planned for 2026; construction contingent on grants and estimated costs range to $3 million
Summary
Commissioners were briefed on Hasmer Lake: staff aim to begin engineering this year and construction next year but funding is uncertain; the Knowles‑Nelson stewardship grant currently has no active funding and full‑build estimates range from about $1 million to over $3 million depending on scope.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Director (speaker 2) told the commission that the Hasmer Lake project is targeted for engineering this year and construction next year, but both steps are contingent on securing funding. The director said one major potential source, the Knowles‑Nelson stewardship grant, currently has no funding available in its former configuration and may return in a different form in the future.
The director outlined two illustrative cost options developed during master planning: a four‑season shelter and related amenities that would push the total toward a little over $3,000,000; and a scaled alternative with an open‑air pavilion, restrooms and limited amenities estimated at roughly $1 million to $1.5 million. Staff said phasing the work and combining grant applications across multiple years are among the strategies under consideration. "That option, we believe would be roughly a little over 3,000,000," the director said of the full shelter option.
The director said the department hopes to have a more definitive plan of action by fall, contingent on grant award decisions and other funding sources. Commissioners asked for ballpark figures; the director reiterated cost ranges and emphasized the funding contingency. No formal commitment of local capital was taken at the meeting.