Westminster approves water‑service and City Hall HVAC contracts; council requests more vetting information
Summary
Council awarded a $870,900 contract (plus 10% contingency) for a Brownstone Lane condo water‑service replacement and a $898,240 contract (plus 10% contingency) for City Hall HVAC replacement; council members pressed staff for past repair costs, contractor experience, and schedule constraints tied to ARPA deadlines.
Get email alerts on the Contracts Procurement topic
No spam. Unsubscribe anytime.
The Westminster City Council voted March 25 to award two infrastructure contracts after staff presented project backgrounds and answered member questions.
Water service replacement: Staff recommended awarding the Brownstone Lane condominium community water service‑line replacement project (Project PD‑2447, 138 units) to the lowest responsive bidder after confirming licensing and references. Maintenance and utility manager Juan Pham told the council the low bidder provided additional documentation and positive reference checks during staff follow‑up.
Council members pressed staff for the frequency and cost of prior emergency repairs in the neighborhood; staff said responses could be compiled and returned to council. The council awarded the water contract to Fuerza Construction in the amount of $870,900 and authorized a 10% contingency of $87,090 for change orders.
City Hall HVAC replacement: Staff then presented the HVAC replacement and associated scope for City Hall (Project PD‑2615), funded with ARPA dollars. The original, broader roofing and HVAC scope was pared to prioritize HVAC; staff expects the roof work to follow. Council questioned whether installing new rooftop HVAC before completing the roof risked re‑work and whether the ARPA expenditure timeline could be met. Staff and the project manager said units are available, preconstruction will begin quickly, and the roofing project will be scheduled to follow.
Council approved the HVAC contract to Simcoe Mechanical Inc. for $898,240 and authorized a 10% contingency ($89,824). Members asked staff to monitor contractor performance closely on public‑facing work and to return figures on prior repair expenses for the water community.
Next steps and oversight: Both contracts include standard public‑works compliance checks (licenses, DIR registration, references). Staff committed to returning with further documentation on past repairs and to closely supervise construction to maintain pedestrian and community safety during night and day operations.