Lifetime Citizen Portal Access — AI Briefings, Alerts & Unlimited Follows
Council hears Capital Improvement Board report on quiet zones, marina engineering and plaza lighting
Loading...
Summary
The Capital Improvement Board reported five funding allocations including design/coordination for Downtown and Hessville quiet zones, preliminary engineering at the Hammond Marina, Downtown Train Station engineering, and Dan Raven Plaza lighting, totaling several discrete awards.
The Hammond Capital Improvement Board reported to the council on March 23 that it had approved five funding allocations for local infrastructure projects.
The board awarded $18,000 to First Group Engineering for design and railroad coordination on a Downtown Hammond railroad quiet zone and $23,000 to the same firm for a Hessville quiet-zone supplemental agreement. It approved $27,739 for preliminary engineering on a screen wall at the Hammond Marina (the marina will cover that fee). The Downtown Hammond Train Station engineering contract was awarded to Neese Engineering for $198,500, and Hawk Enterprises received $135,353.32 for lighting and electrical improvements at Dan Raven Plaza.
The council member reporting the allocations said those five awards comprise the full set of funding items from the Capital Improvement Board and thanked members for their work. No objections or amendments were recorded and the council moved on to other business.