Committee accepts $258,656.45 contract credit for South and Central Lafourche athletic-field repairs
Summary
Officials granted substantial completion for athletic fields pending a power-meter turnover, accepted a net contract credit of $258,656.45 reflecting FEMA-required deletions and added 105 days to the project schedule to avoid disrupting the baseball season.
Get email alerts on the Athletic Fields topic
No spam. Unsubscribe anytime.
The Land and Facilities Management Committee accepted a change order on March 18 that yields a net credit of $258,656.45 and adds 105 calendar days to the South and Central Lafourche High School athletic-field repair contracts.
The district’s project manager reported that Central Lafourche’s field work is complete and South Lafourche remains finished except for power-meter turnover. To avoid interrupting the baseball season, staff recommended granting substantial completion with a punch-list item for the power changeover and extending the contract schedule by 105 days.
Staff explained that FEMA requirements and value engineering altered the scope: press-box requirements FEMA would not allow were removed (a $143,000 deduction) and a permanent concession stand was deleted because FEMA determined the previous structure was a portable building (a $145,000 deduction), partially offset by a $29,700 modular concession add-back. The net effect is a credit of $258,656.45. "So that will close out the project except for…that substantial completion," the project manager said.
A motion to accept the change order (moved by Miss Fabin, seconded by Miss Bourgeois) passed by voice vote.
District staff said the timetable adjustment and the substantial-completion approach are intended to keep facilities available for ongoing athletic seasons while finishing final utility work off-season.