Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Contracts And Procurement topic

No spam. Unsubscribe anytime.

MIPFA approves $1,495 Tetra Tech claim for Pensacola GRDA relicensing; litigation budget balance noted

MIPFA · January 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The MIPFA approved a $1,495 claim from engineering firm Tetra Tech for work tied to Pensacola GRDA relicensing; staff said the payment would leave $695,716.80 of a $750,000 litigation budget for the year.

The MIPFA approved a $1,495 claim from engineering firm Tetra Tech for work on the Pensacola GRDA relicensing during its regular meeting.

The trust manager explained the invoice supported civil‑litigation modeling by Tetra Tech and said, "If this is approved tonight, it'll be remaining balance of $695,716.80 of the 750,000 that we budgeted for the year." A motion to approve the claim was made, seconded and recorded; members responded in roll‑call and the motion passed.

Why it matters: Trustees flagged the cost against a $750,000 annual budgeted amount for litigation and related work, signaling available funds for ongoing legal matters tied to the GRDA relicensing effort.

Votes at a glance: 5a (claims list) — approved; 5b (minutes of 12/16/2025) — approved; 5c (Tetra Tech claim, $1,495) — approved. Individual vote names were read into the record during roll‑call and recorded as in the meeting transcript.

The meeting then moved on to other agenda items and was later continued for an executive session. No additional detail on the GRDA relicensing work scope or contract terms was provided in the public portion of the meeting.