Council approves $1.79 million Harbor Pacific change order for wastewater plant, adjusts sewer fund totals
Summary
The Granite Falls City Council approved a consent-agenda change that included a $1,790,922.13 change order for Harbor Pacific’s Wastewater Treatment Plant work, raising CIF Sewer fund claim totals and increasing the meeting’s overall claims to $2,203,142.54.
Get email alerts on the Wastewater Treatment topic
No spam. Unsubscribe anytime.
The City Council approved updates to the consent agenda that included a $1,790,922.13 change order for Harbor Pacific on the city’s Wastewater Treatment Plant project and an additional claim of $33,500 to Impact Repair & Excavation.
Deputy City Manager Jeff Balentine told the council the Harbor Pacific change order increases the CIF Sewer fund claims from $7,073.65 to $1,797,995.78 and raises the grand total for claims to $2,203,142.54. He also noted Check #414956 to Impact Repair & Excavation for $33,500, which changed the Sewer fund totals from $24,977.65 to $58,477.65.
Councilmember Griggs moved to approve the consent agenda with the reported changes; Councilmember Straughn seconded and the motion carried. The minutes list the result as "Carried" but do not include individual roll-call tallies.
Public Works Director Charles White provided a general update on the Wastewater Treatment Plant as part of his staff report; specific technical details of the plant update were not listed in the minutes. The council did not take additional separate action on the plant update at this meeting.
Next steps: the change order and adjusted claims were recorded as part of the approved consent agenda. The minutes do not specify further council direction, contract amendments, or a project schedule change at this time.