District gives construction update, Elementary School Eight out to bid; district readies mailers and outreach
Summary
The district reported that 14 bundled construction projects are in various phases, Elementary School Number Eight is out to bid with final bids expected in March and contract in April, and communications staff will mail a district newsletter and hold an open house Feb. 18.
District staff provided a construction and communications update at the Jan. 14 meeting, detailing project timing and community outreach plans tied to upcoming bids and bond work.
Robb Stanton, Executive Director of School Planning & Construction, said 14 projects are bundled into five major and three minor groupings and are at varying phases: some moved into permitting…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat