Metro District seeks $300,000 appropriation and IGA amendment for Dad Clark Gulch channel stabilization
Summary
Project Engineer John Donakowski presented a plan to restore roughly 3,000 linear feet of Dad Clark Gulch channel to reduce sediment and protect downstream water-quality facilities, requesting a $300,000 appropriation from the District and authorization to amend an IGA with Mile High Flood District for $600,000 in construction funding; item was placed on the Jan. 27 consent agenda with no objection.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
Project Engineer John Donakowski presented the Dad Clark Gulch 5.0W channel stabilization proposal, describing approximately 3,000 linear feet of channel restoration north of Wildcat and east of Summit View intended to prevent downstream degradation and reduce sediment impacts on water-quality infrastructure.
Donakowski asked the Board to appropriate $300,000 from the Stormwater Fund as the District’s share and to authorize an amendment to the existing Intergovernmental Agreement with Mile High Flood District for a $600,000 construction contract, with $300,000 funded by the Metro District. He told the Board that current site conditions do not threaten structures or pathways but that the work is timely to protect downstream facilities. Board members asked questions that Donakowski answered; Chairperson Anderson noted no objection to placing the item on the Jan. 27 consent agenda for formal Board action.