Owasso Public Works Authority authorizes $58,755.60 payment to Kellogg Engineering for Bird Creek emergency water-line work
Loading...
Summary
Trustees approved a staff recommendation to pay Kellogg Engineering $58,755.60 for engineering and survey work on the emergency Bird Creek 12-inch water transmission line replacement. The board was told the line leaked in December 2025, was repaired by Creek Construction, and an as-built survey was received Feb. 20, 2026.
The Owasso Public Works Authority voted to authorize a $58,755.60 payment to Kellogg Engineering LLC to cover engineering, design, geotechnical and survey services related to an emergency replacement of a 12-inch Bird Creek water transmission line.
Roger Stevens presented the item, saying staff identified a major leak in the 12-inch transmission line under a Bear Creek tributary on Dec. 10, 2025. "As a result, on 12/11/2025 staff informed Kellogg Engineering to commence with the engineering design of the 12 inch transmission line as a result of being an emergency," Stevens said. He told trustees Kellogg completed the design Dec. 22, 2025, and staff received an as-built survey on Feb. 20, 2026.
Stevens said the city solicited three quotes for construction; Creek Construction LLC submitted the lowest bid at $698,200 and received a notice to proceed on Jan. 5, 2025. Stevens reported Creek Construction completed the work Feb. 12 and that funding for the engineering services is available in the Owasso Public Works Fund.
After Stevens recommended the payment to Kellogg Engineering of Tallalla, Oklahoma in the amount of $58,755.60, a trustee praised the pace of the response and moved to approve the recommendation. Stevens seconded the motion. In roll-call confirmations those recorded as voting "yes" included Paul Loving, (transcript: "Mister Loving"), and the trustees recorded under the names read on the agenda; the motion carried and the payment authorization was approved.
The board then moved through routine items: the OPWA manager reported no items for Item 6, the authority acknowledged official notices, and with no new business the board adjourned.
The payment authorization approved at the meeting covers the engineering and surveying work Kellogg Engineering provided after the December leak; the construction contract and payment to Creek Construction were described in the presentation but the approval at this meeting was for Kellogg's engineering services only. Details listed in the staff presentation include the leak date (Dec. 10, 2025), design completion (Dec. 22, 2025), low construction bid ($698,200), notice to proceed (Jan. 5, 2025 as reported) and receipt of the as-built survey (Feb. 20, 2026).
No ordinances, statutes, or other legal authorities were cited in the presentation. The item was recorded as funded from the Owasso Public Works Fund. The meeting adjourned after routine business and no further action on this item was scheduled at the end of the transcript.