Owasso staff reports progress on Garnet Road, US‑169 widening and 86th Street bridge design
Summary
Public works staff reported ongoing work on Garnet Road (waterline relocation), upcoming milling/overlay projects, US‑169 widening beginning Feb. 16, and a bridge replacement design for 86th Street intended to meet 100‑year flood capacity.
Roger Stevens delivered the city’s monthly project status report Wednesday, describing progress and near‑term schedules for multiple transportation and public‑works projects.
Stevens said contractors remain engaged on the Garnet Road improvements (106th to 116th) with water‑line relocation underway and a progress meeting scheduled; staff warned the project could run 3–4 months behind the current schedule if deficiencies are not…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat