City says new water-treatment plant expected to produce potable water by mid-April

Oak Ridge City Council · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials said contractor Bowen Engineering provided an updated schedule that projects continuous potable production from the new treatment plant starting April 23, with demolition of old raw-water lines on May 6 and final completion by Aug. 14; staff reported recent progress including pump tests and membrane contractor coordination.

Water-department staff updated the council on progress at the new water treatment plant and a revised contractor schedule.

Carrie A. Bacon said Bowen Engineering provided an updated progress schedule after management engagement and that continuous potable production is shown to begin April 23; the contractor expects to demolish the old raw-water lines on May 6 (the project’s substantial-completion marker) and reach final completion by Aug. 14. Bacon said some delay from the original February final-completion date remains, but that the April production target is encouraging.

“We're showing April 23 as when they begin to have a continuous production of processed water, potable water, from the new water treatment plant,” Bacon said.

Staff reported recent 'bump' tests of the new raw-water pumps and that the contractor brought additional managerial and supervisory staff to the site. The city’s membrane vendor Wiggins will assist with membrane installation and process-control start-up; staff planned multi-hour startup coordination with that vendor.

Council members asked whether the booster station and hilltop treatment plant would still be needed; staff said the hilltop facility will no longer be necessary for treatment once the new plant is operational but that some tanks and maintenance buildings will remain in use. A charter provision governs disposal of unused facilities, staff said.

No council action was required; staff will continue to monitor contractor progress and keep the council informed.