Rochester Hills OKs $1.13 million design-build contract for fire training tower

Rochester Hills City Council · August 27, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a not-to-exceed $1,131,305 award to AR Brower for a modular live-fire training tower at headquarters; staff said budget overruns will be covered by shifting funds from a canceled trailer purchase and underspent station projects so no fund-balance use is required.

The Rochester Hills City Council on Monday authorized a design-build contract with AR Brower Company of Dexter for a modular live-fire training tower at Fire Station headquarters in a not-to-exceed amount of $1,131,305.

Fire Department representatives said the existing tower — more than 30 years old — lacks live-fire capability and that the proposed modular tower includes multiple live-fire training rooms and reconfigurable interior and exterior walls to vary training scenarios. The design-build approach was chosen to combine design and project management with supplier coordination for a specialized facility.

Council members noted the award came in above the $900,000 budgeted figure. City staff explained the department will not replace a $165,000 public-safety education trailer and anticipates savings of about $66,000 on an HVAC/roof and locker-room rehabilitation at Fire Station No. 1; together those adjustments are expected to cover the overage without using fund balance.

Deputy Chief Cook explained that the design-build procurement includes parameters set in the RFP and that an approved design will be finalized before construction begins. Councilmember Mangioli and others voiced support for the training benefits; Councilmember Mongeoli noted the use of fire-millage funds was appropriate for the public-safety investment.

Council approved the contract and authorized the mayor to execute the agreement on behalf of the city.