City staff update council on CSO phases, firehouse work and paving plans
Summary
City staff told the council that the next combined-sewer-overflow (CSO) phases will be bid soon, Firehouse Engine 2 demo is complete with concrete pour planned, Foschini Park site work is underway, and CDBG and county paving schedules were outlined — PSE&G utility work will add roughly 18,000 sq. yards of resurfacing.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Ryan, the project manager, briefed the council on ongoing infrastructure projects and near-term schedules. He said the next two CSO phases (west-of-rail Phase 1 and a Phase 2 area) are imminent: "we should be bidding that, shortly," and the work will move through bidding and construction over the coming months.
Ryan reported that Firehouse Engine 2 demolition is complete, inspectors signed off on rebar work, and the contractor is scheduled to pour concrete on Thursday the 16th; he advised a roughly three-week cure time before equipment returns. He also described Foschini Park site-preparation (drainage, geogrid, DGA stone), the city’s CDBG roads (South Newman and DeWolf) slated to start at the end of the month with expected completion before Thanksgiving, and a county plan to install ADA ramps on South River Street followed by milling and paving. Ryan told the council PSE&G gas-main work has driven an additional ~18,000 square yards of resurfacing that the city will add to its paving plan.
Councilmembers asked clarifying questions about paving limits (five-year curb-to-curb rule vs. centerline-to-curb on older streets) and confirmed coordination with county contractors. No formal actions were taken; the presentation provided schedule and scope updates for staff follow-up.