Commission approves six utility buildings at LADWP site; commissioners press for follow-up on wastewater and infrastructure
Summary
Adelanto planners approved a location and development plan to build six utility and equipment buildings at an existing LADWP site after staff said the project meets Public Utility Zone standards and would be subject to a Mitigated Negative Declaration; one commissioner abstained from the final vote.
Get email alerts on the Utility Infrastructure topic
No spam. Unsubscribe anytime.
The Adelanto Planning Commission on Jan. 15 approved Location & Development Plan 24-13 to construct six utility and equipment buildings at an existing Los Angeles Department of Water and Power site in the city’s public utility zone.
Planner Christian Espinosa outlined the proposal — six structures including an AC filter relay building (about 2,226 sq ft), a spare parts building (about 11,476 sq ft), medium-voltage switchgear buildings and a microwave communications building — and said staff determined a Mitigated Negative Declaration was the appropriate environmental document after public circulation. Espinosa recommended adoption of Resolution P-25-02 and approval of the plan subject to conditions.
Agency representatives said the project will replace aging infrastructure at a site that has been in operation for decades. In response to resident concerns about water consumption and sewer discharge, an agency speaker said the proposed plant would operate as a closed system and that water consumption and sewer discharge are conservatively expected to be reduced by about 50% compared with the current cooling system: "The future plant is going to be closed system, so the expectation is the water consumption and sewer discharge is conservatively reduced by about 50%." Commissioners asked about phasing and decommissioning of older equipment, and staff said the old buildings would be decommissioned as new ones come online.
Residents and Mayor Gabriel Reyes urged follow-up conversations with LADWP about wastewater discharge and possible partnerships to address needed city sewer upgrades. The commission adopted the staff recommendation; the vote passed with four yes and one abstention.