Marion Water Department outlines major projects and proposes 3% rate increase
Summary
The Marion Water Department proposed pulling $2.6 million from reserves to balance an expanded FY27 budget and flagged a potential 3% water rate increase with a public meeting scheduled for June 9; department leaders reviewed several water-main projects and the new elevated Lucor tower timeline.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
Todd Steigerwalt, general manager of the Marion Water Department, told the Marion City Council on April 7 that the department’s proposed FY27 budget is up by nearly $500,000 from last year and that staff plan to transfer $2,600,000 from cash reserves to balance revenue and expenses.
Steigerwalt outlined major capital work driving the budget: Phase 2 of the 1st Avenue reconstruction, sewer trunk projects along Central Avenue, multiple water-main abandonment projects (bids reported for South 15th Street and Brookside Drive), and a rising Lucor elevated water tower that staff expect to be filled and put into use in summer or 2027. He also reported the department’s cash balance at about $13,000,000.
On rates, Steigerwalt said the department is proposing a 3% water-rate increase and will hold a public meeting on June 9 at 4 p.m. He explained the increase is motivated by inflation and rising energy and fuel costs and showed example customer impacts: the department estimated a two-month minimum bill would rise by $0.22 and an average two-month bill (1,200 cubic feet) would rise by about $0.54.
Council members asked about the size of the reserve transfer and the department’s longer-term projects; Steigerwalt said more projects are on the horizon and that some water purchases from Cedar Rapids will increase (Cedar Rapids notified Marion of a 6% increase for water purchased for Glenbrook Cove). Several bids for local projects were noted (e.g., Rachi Construction as low bidder on Brookside Drive at $71,531).
No formal council vote was taken; the presentation concluded with staff available to return with more detail and to hold the June public meeting on rates.