Board approves resolution to execute HVAC change order after vendor mis‑measurements; district to pursue recoupment
Summary
The board approved Resolution 1655‑24 to authorize a construction change order for rooftop HVAC installations after staff explained that vendor Siegler mis‑measured roof curbs; ESSER funds pay the installer now and staff said they will pursue credits or reimbursement from the vendor.
The Chico Unified School District Board on Aug. 21 voted to adopt Resolution 1655‑24 authorizing execution of construction change order number 003 related to rooftop HVAC package installations at multiple school sites.
Julie Kissel, presenting the item, described the timeline: the district purchased HVAC units with ESSER (federal COVID relief) funds and engaged a contractor (UBC) to remove existing units and install new equipment on a compressed schedule that included helicopter deliveries. Once installation began, staff found many of the pre‑purchased roof curb adapters did not fit.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat