Ventnor outlines boardwalk replacement plan and federal-state grant funding; $7.5M must be spent by Dec. 2026
Ventnor City Commission · March 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Officials said boardwalk decking materials have been purchased and that roughly $7.5 million in grant funding must be spent by December 2026; the town plans phased construction beginning September 2025 and is applying for an additional $5 million grant.
City staff and commissioners described progress on the boardwalk replacement project during the March 13 meeting, telling the commission that decking and fasteners have already been procured and that the broader project carries multi-million-dollar grant commitments.
A staff member said…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans