Staff says PO for RTUs issued after accounting fix; chair warns late fire‑system orders pose project risk
HVACI Q building committee · April 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Staff reported a purchase order for RTU1920/22 will be issued after accounting corrections and estimated a six‑to‑eight‑week lead time; the chair warned that delayed ordering of fire‑system devices (Sonitrol) risks project schedule and fire‑marshal approvals because devices must be in hand before work begins.
During old business, staff (S9) told the committee that purchase orders for RTU1920 and RTU1922 will be or have been issued after accounting corrections, and that expected lead time for the units is six to eight weeks.
"PO will be issued. We found the money," S9 said,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans