Pre-application workshop held for 29-acre conservation subdivision on Bruce Hill Road
Summary
At a public workshop, the applicant presented a sketch plan for a 29-acre conservation subdivision at 147 Bruce Hill Road proposing conservation/open-space, 75-foot buffers, municipal water extension and on-site septic. Abutters raised access and deed-restriction concerns; board directed the applicant to submit a full preliminary packet for peer review.
Get email alerts on the Subdivision topic
No spam. Unsubscribe anytime.
The Cumberland Planning Board heard a pre-application presentation for a proposed conservation subdivision at 147 Bruce Hill Road, a roughly 29-acre parcel in the RR2 district.
Henry Hess, a landscape architect with Sebago Technics, presented the sketch plan and described a layout that keeps the rear of the parcel in conservation, provides a roughly 75-foot buffer around the lots, anticipates municipal water extension from Bruce Hill Road, and relies on on-site septic (no sewer currently available). Hess said wetlands on site are small, mostly forested pockets that the plan does not propose to impact and that the long-term goal is for conserved land to be donated to the town.
Board members and abutters focused on access: several speakers noted an abutter's driveway that runs along the parcel line and raised concerns about preserving continuous and emergency access during construction. Hess said the preferred approach is to maintain an easement through proposed open space and to confirm utilities and deed language; Bridgette the town planner said the applicant bears the burden to demonstrate title and any deed restrictions in the forthcoming packet.
Members also asked about spring timing for vernal-pool assessments and rare-species notifications; Hess said the team will notify state agencies and may not need a vernal-pool study if site indicators are absent. The board reiterated the process: a full preliminary application with technical submissions, peer review by the town engineer, a public hearing and a final submission. The board recommended the conservation subdivision approach and scheduled a site visit; staff said three meetings (preliminary and final included) are likely as the project advances.
Next steps: the applicant will submit a detailed preliminary plan, including deeds/title searches, traffic, wetlands, groundwater and septic/percolation tests, and agency coordination for rare species. The board said staff and peer review will examine whether any relief (setback or buffer waiver) is appropriate for an existing structure on the parcel.