Airport staff report January finances; board discusses grant shortfall
Summary
Staff reported January revenue slightly above budget and expenses slightly below; passenger traffic was up about 2.4%. Members raised concern that state funding was cut from an anticipated $60M to $45M and urged legislative follow-up for the missing $15M.
Get email alerts on the Financial Report Jan2026 topic
No spam. Unsubscribe anytime.
Airport staff presented the authority’s January financial recap and forecast, noting revenue categories (parking, aeronautical and other) and a pending audit expected next month. Tana told the board January revenue was slightly above budget while expenses were slightly below, and passenger traffic in January increased about 2.4% year over year.
Tana said the authority has been conservative when forecasting conditional grant awards, budgeting 50% of conditional amounts; the confirmed $45 million award was therefore incorporated into the forecast after reconciling earlier assumptions. The board discussed an unresolved $15 million reduction from the original $60 million request and several members urged continued engagement with the state legislative delegation to restore funding in the next biennium.
Finance discussion also included parking KPIs and the status of a Bank of North Dakota loan drawn for terminal and parking construction; staff reported approximately $39.4 million of a $40.0 million loan outstanding. Staff said they will continue monthly reimbursements requests to FAA and state grant administrators.
The board voted to receive and file the financial report.