Council approves Meadowlark/Loma Largo drainage and paving project; residents warned of closures
Summary
The council approved Resolution 24‑14 to advance drainage and paving work including Upper and Lower Meadowlark with expected closures; public‑works staff described schedule and anticipated 3–4 week duration for Lower Meadowlark.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Corrales Village Council approved Resolution 24‑14 (TPF project approval) to advance drainage and paving work along Loma Largo and Meadowlark lanes after staff described construction sequencing and flood‑control design.
Public‑works representative Steve Lisku told the council Upper Meadowlark curve and gutter work should be complete by the end of the week and that paving would follow; Lower Meadowlark was expected to begin around the 22nd and to take roughly three to four weeks. Lisku said contractors and the police will assist to secure project areas and limit intrusions during work hours; full closures for resident access only were anticipated.
Council and staff discussed storm‑event standards (project engineered for a 100‑year flood standard) and retaining‑wall choices; staff said the project is shovel‑ready. Councilor Murray moved for approval and the resolution passed by roll call.
Residents had earlier raised safety concerns (speeding on Andrews/Amherst and barricade circumvention), and staff said they would pursue enforcement and adjust closures during work hours to reduce risk to residents and crews.
What passed: Resolution 24‑14 (TPF project approval) was approved; staff will coordinate closures, striping and final paving details and report progress at future meetings.