Citizen Portal
Sign In

Lifetime Citizen Portal Access — AI Briefings, Alerts & Unlimited Follows

Authority staff outline multi-year pump-station rehab and several projects including a residence replacement

McGee Creek Authority · March 12, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mark Long reported on multiple capital projects: an MCA residence contract awarded to Browns Construction for $339,816 (completion planned May 2026, staff seeking recovery plan), a $250,000 BOR-driven repair package with bids due May 27, and a major multi-phase pump-station rehabilitation slated for completion by December 2028.

Mark Long delivered a capital-improvement program status update covering several active and upcoming projects at McGee Creek.

He said contract WMC-037-1 (MCA residence replacement) was awarded to Browns Construction in May 2025 for $339,816 with framing underway; Long said he will meet the contractor to request a recovery schedule after observing that roof trusses were not yet installed and that progress may threaten the May 2026 completion date. Long told trustees he would seek a recovery plan from the contractor.

Long described WMC-042, a Bureau of Reclamation inspection-driven package for drainage and miscellaneous repairs with a scheduled bid opening May 27 and an estimated cost of $250,000, covering outfall and drain repairs, mold and water damage remediation to sheetrock, tunnel ventilation and corroded electrical conduits.

Other projects include WMC-044 (structural and coating improvements addressing corroded steel members and support structures, with preliminary engineering completed in December), WMC-046 (MCA headquarters site restoration once the residence is complete, including hazardous-material inspections for lead paint and asbestos and a planned summer bid), and WMC-035-2 (facility road repairs to Ferris Road and Crossover Road to be scheduled after demolition and construction to avoid damage). Long emphasized the significance of WMC-047, a multi-phase pump-station rehabilitation to replace antiquated electrical and instrumentation controls, consider motor replacements and potentially expand the building for new control equipment; Long said the pump-station work will likely proceed in phases to maintain operation and is planned to be completed by December 2028.

Trustees asked follow-up scheduling questions and expressed concern about the residence timeline; Long said staff will press the contractor for a recovery plan.