Facilities director details projects; board accepts roofing bid and approves contingency process for high-school modernization
Summary
Facilities staff updated trustees on restroom, modernization and DSA issues including missing insulation found in demo; board accepted a roofing bid for Las Banos High and approved a staged change-order contingency process to avoid delays while preserving oversight.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The board on Feb. 11 approved a roofing bid and a contingency change-order process for the Las Banos High School modernization after receiving a multi-site facilities update.
Facilities staff reviewed ongoing projects: a new restroom building at Miano (expected in-service by late March), certification and landscaping work at the early-education center with traffic-signal programming in progress, Volta Elementary modernization including windows and interior finishes, and continued demo and abatement work at Las Banos High School Wing H. The director said crews discovered missing insulation in walls and ceilings during demo, which does not meet Title 24 standards and will require corrective work.
Facilities said the Lofton Stadium Phase 3 submission to the Division of the State Architect (DSA) has been delayed because DSA cannot find documentation for a prior change order to the press box and restroom area; the district is pursuing reverse engineering to prove structural adequacy or may need to demo and rebuild non-approved modifications.
Trustees then accepted a bid from DD Construction, Inc. for Category 7 (roofing, sheet metal and flashing) on the Las Banos High modernization. They also approved a contingency budget and approval thresholds to process change orders more efficiently: project manager approval up to $50,000; $50,000–$100,000 requiring signatures of Dr. Lee and Dr. Ritchie; and amounts over $100,000 brought to the facilities subcommittee or full board.
"We created a document for tracking so you guys should have a copy of this," the facilities director said, explaining the intent to minimize project delays while maintaining oversight.
Why it matters: The modernization and safety work impacts school operations, timelines for facility use and the district's construction budgets. The contingency process aims to balance timely construction decisions with board-level accountability.
What's next: Staff will proceed with awarded roofing work, implement the change-order approval workflow and continue to work with DSA to resolve the Lofton press-box documentation issue.