Hertford streetscape grant bid comes in at $1.2M; town to negotiate, may need $45,000 more
Summary
A single bidder submitted $1.2 million for a $725,000 streetscape/connectivity grant project; after design and engineering obligations the town has $654,200 in remaining grant funds and designers are negotiating with the bidder to reduce scope toward $700,000, leaving a potential $45,000 town funding gap plus additional vegetation and electrical costs.
Get email alerts on the Streetscape Connectivity Grant topic
No spam. Unsubscribe anytime.
Manager Doris Walton told the council on March 23 that the Town of Hertford received one bid—B.E. Singleton—for its streetscape/connectivity project and that the bid totaled about $1.2 million, well above the $725,000 grant award. Walton said the budget had $654,200 remaining after paying for design and engineering and that the project designer and architect were negotiating with B.E. Singleton to lower the cost toward a $700,000 target. If the bid cannot be reduced to that level, Walton said the town would need to identify roughly $45,000 in additional funds; she also noted vegetation and electrical work would add costs but could be handled in part by town staff.
Why it matters: The streetscape project is grant-funded but the single bid exceeds available grant funds, forcing the town to consider scope reductions, negotiate price, or provide local match dollars to proceed.
What was said: Walton described ongoing negotiations with the single bidder and the need to find additional funds if scope cannot be reduced; designers and architects will pursue a scope reduction to bring the project closer to available funding.
Next steps: Designers will continue negotiations with B.E. Singleton; if negotiations fail, council will need to identify additional funds or modify the project scope. Manager Walton said she will report back when negotiations conclude.
Attribution and uncertainty: Statements about bid values and remaining grant funds are drawn from the manager’s update in the meeting minutes; the manager characterized FEMA’s BRIC grant as “on hold” because FEMA was not being funded at the time, a status that may change and should be confirmed with grant administrators.