Yolo County Animal Services staff briefed the board March 24 on operations, services and an ongoing facilities modernization effort. Presenters described 2025 intake and outcomes (803 dogs and 1,205 cats adopted in 2025), current staffing levels, veterinary services capacity, partnerships with rescue groups and volunteers, and plans to deploy a mobile or modular surgical clinic (the “clinic‑in‑a‑can”) and to issue an RFP for community partners to operate renovated county space (the 2A building).
Director-level staff and the animal‑services presenter outlined deferred‑maintenance work already completed (new roof, HVAC and lighting upgrades), identified remaining electrical and drainage issues at the shelter and said one of the county’s priorities is to avoid cost overruns by completing a full engineering bid package before issuing construction contracts. Staff expect to release the RFP in mid‑April, with an eye to having grant awards or service agreements in 2027 after procurement and contracting steps.
The presentation highlighted partnerships that boost adoptions and medical capacity, including the Spay Neuter Project (SNP) and Friends of YCAS. Presenters described volunteer growth (e.g., kitten foster parents) and community clinics that served hundreds of pet owners; they also noted increased owner surrenders amid housing instability and rising resource needs for TNR (trap‑neuter‑return) work.
Multiple rescue and advocacy speakers during public comment praised staff, urged faster deployment of clinic capacity and recommended stronger volunteer and foster programs, expanded adoption hours and clearer metrics to measure program success. Supervisors asked staff to continue coordinating early with city partners and to include potential budget implications in the county’s upcoming budget process.
Board members and staff said they will return to the board with RFP timing and budget details; staff confirmed they are planning to present RFP materials and plan to include the JPA and city partners in outreach and future briefings.