Board approves priority water-softener replacement and budgets staged heater repairs
Summary
After facilities staff traced equipment failures to an undersized water-softening system, the board approved replacing the central softener for $14,561.34 and authorized initial heater work with Pioneer Plumbing (initial scope ~$15,270), with remaining units to be budgeted next fiscal year.
Get email alerts on the Facilities Repairs topic
No spam. Unsubscribe anytime.
The Pittsville School District board approved priority repairs to address chronic water-quality problems that staff say have shortened the life of water heaters and other fixtures.
Facilities staff (Speaker 7) described a residential-style water-softening system installed in a commercial building that is undersized for campus flow demands and is causing buildup and premature failures in downstream equipment. Staff presented multiple quotes and recommended immediate replacement of the central unit; the replacement price cited in the discussion was $14,561.34 for the prioritized system.
The board voted to approve the Countryside/Culligan proposal to replace the identified softener. The motion to approve the Countryside Culligan water-proposal was moved, seconded and advanced in open meeting.
Facilities staff also presented estimates to replace multiple water heaters: two large locker-room units priced at about $13,070 each (roughly $26,140 for both) and a kitchen heater install priced around $2,200. Staff recommended replacing one high-priority locker-room unit now and budgeting the remaining replacements in the next fiscal year, to avoid a single-year spike in capital expenses.
The board approved an initial contract with Pioneer Plumbing to purchase and install the above-locker-room unit and the elementary-kitchen heater (initial amount presented as $15,270) and authorized staff to proceed with the additional units if surplus funds materialize.
Board members discussed warranty implications, lead times and sequencing so the new boilers and warranties would not be compromised. Staff emphasized purchases would not be executed unless the surplus revenue is confirmed.