Board approves change order 12 for Milpitas High performing-arts center; construction manager says January ribbon-cutting remains on track

Milpitas Unified School District Board of Education · September 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved Swinerton change order No. 12 to cover tariffs, PG&E-related work and fire-pump electrical runs for the Milpitas High School performing-arts center; construction management reported project change orders at 7.08% and said the team expects completion and a January ribbon-cutting.

Trustees voted to approve Swinerton change order No. 12 for the Milpitas High School performing-arts center after construction management summarized recent costs and schedule impacts.

Travis Kirk, representing construction management, said the change order includes a small tariff-related charge for metal panels, additional work triggered by PG&E coordination, and the electrical run necessary for a fire pump above the theater stage. He described one instance where contractor labor estimates were reduced after moving from a flat-rate estimate to time-and-material tracking, saying that saved labor hours and costs.

Kirk reported the project is currently trending at 7.08% in change-order costs but characterized that as favorable compared with other lease-leaseback projects he has seen. Trustees asked about schedule and student occupancy; Kirk said the team remains on track for January and that student move-in for the second semester is probable but a site-level decision would be made by school leadership.

A trustee requested that students be among the first to use the facility; the board deferred the final decision about external rentals to the chief innovator and superintendent. The motion to approve the change order was made, seconded and carried by voice vote.

No public comments were recorded on the item.