Commissioners amend Lakeview DDA/TIF plan to prioritize roadway infrastructure
Summary
The Battle Creek City Commission approved introduction of ordinance O2-2026 and an amendment that moves roadway infrastructure to a higher funding priority while lowering the priority for events in the Lakeview DDA/TIF plan; commissioners discussed oversight and how captured tax increment might be used.
Get email alerts on the Ldda Tif Amendment topic
No spam. Unsubscribe anytime.
The Battle Creek City Commission voted to introduce ordinance O2-2026, which updates the Downtown District Authority (LDDA) and tax increment financing (TIF) plan for the Lakeview area, and approved an amendment that elevates roadway infrastructure development to a high priority while lowering events to low priority.
Commissioner Pat (Chris) Simmons, who said he helped shepherd the plan and brought the amendment, argued the commission should focus captured funds on public infrastructure first. "Everyone that drives the Beckley Road corridor will agree that it has major issues," Simmons said, noting the corridor had not seen major updates for decades and that infrastructure investments should come before event programming.
Commissioners discussed cost items and oversight. Simmons noted large line items in planning materials — including an estimate of roughly $50 million for some site work — and said staff’s decision to pause implementation allowed the commission time to examine priorities and constituent feedback. He said the city manager and an added city commissioner on the LDDA board will improve communication between the LDDA and the commission.
Commissioner Patrick O'Donnell echoed the infrastructure concern, saying roadway improvements would increase safety and travel reliability. The commission approved the amendment and the introduction of O2-2026; the clerk read that the Planning Commission previously reviewed related petitions and public engagement had occurred.
Why it matters: shifting TIF priorities from events toward infrastructure directs scarce incremental tax dollars toward repairs, transit amenities and roadway work in a major commercial corridor, which proponents say addresses long-running traffic and stormwater issues. Opponents previously raised questions about large cost estimates and the need for oversight to ensure the LDDA contributes appropriately to public services.
Next steps: The ordinance was introduced for consideration; further hearings and detailed budget items will follow as the LDDA/TIF plan proceeds through the ordinance process.