Charles Mix County awards multiple 2026 road and bridge contracts, approves Wahehe Township bridge replacement

Charles Mix County Board of Commissioners · March 26, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board unanimously approved Hollaway Bridge to replace Wahehe Township Structure #12-40-368 for $242,670 and accepted multiple 2026 bids—including a $2.96 million overlay on County Road 34 and countywide asphalt and chip/fog-seal contracts—during its March 26 meeting.

The Charles Mix County Board of Commissioners on March 26 awarded a series of highway contracts for 2026, approving a $242,670 contract with Hollaway Bridge and Culvert to replace Wahehe Township Structure #12-40-368 and accepting several sealed bids for paving, chip/fog sealing and equipment services.

Highway Superintendent Doug Cimpl reviewed planned bridge repairs and the Geddes Oil Road project before the board voted. Chairman Colin Soukup moved to contract Hollaway Bridge and Culvert for the Wahehe Township bridge replacement; Vice Chairman Kory Standy seconded the motion, and it passed unanimously. The minutes state the contract price as $242,670.

The board opened sealed bids for countywide asphalt patching and accepted Spencer Quarries Inc./Commercial Asphalt’s bid of $125 per ton (with several loading-price options listed in the minutes) for County Wide Asphalt Patching. Spencer Quarries was also the apparent low bidder on a 10.0-mile, 3-inch-mat overlay for Project Segment 54 (County Road 34) at $2,959,200; the board accepted that overlay bid until the next bid letting notice.

For chip/fog-seal work on Segment 23-38 (County Road 49, 8.52 miles), The Road Guy Construction Co. Inc. submitted a combined bid of $326,361 ($264,947 for chip seal, $61,414 for fog seal) and the board voted to accept that bid until the next bid letting notice. The minutes list Hollaway Bridge and Culvert’s equipment and labor hourly rates and show the board accepted Hollaway’s bridge-repair package until the next bid letting notice.

Commissioners also opened a long list of contractor equipment bids from local and regional firms and voted to accept all submitted Road Machinery Services bids until the next bid letting. True North Steel’s bids to supply metal pipe, guardrail, steel decking, timber bridge products and prefabricated modular steel bridges were likewise accepted.

All highway-related motions recorded in the minutes passed by voice votes with motions typically moved by Standy and seconded by Stotz.

Next steps listed in the minutes indicate the accepted bids will be held “until the next bid letting notice,” and individual projects will proceed under the awarded contracts and applicable procurement rules.