Tustin staff outline playground, park and public-art updates; Legacy Park Phase 2 to be value-engineered

Tustin Community Services Commission · March 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Deputy Director Buescher and Director Clann reported the new playground’s pour is complete with an April 10 readiness target; Old Town curb-and-gutter and parklet work is underway; Legacy Park Phase 2 will be value-engineered to reduce costs with a projected 2027 finish; a community-designed mural at the Tustin Family Youth Center and a micro-gallery pilot with Tustin Unified were also discussed.

Deputy Director Buescher told commissioners that cement work for a new, universally accessible playground is complete and the play area inspection and finishing steps are expected in early April, with a goal of opening by April 10. Staff also said picnic-shelter materials are moving through plan check and the shelter project should be ready for a summer grand opening once materials arrive.

Work in Old Town is progressing with curb-and-gutter installation and a partial closure of El Camino Real to allow parklet construction while keeping one travel lane open so businesses can remain accessible. Staff said they are coordinating schedules to host a first sunset market on May 21.

On Legacy Park Phase 2, Director Clann said the project will undergo a value-engineering review in the coming months to reduce scope and cost; officials expect bidding in the second half of the year and a phased completion in 2027. The review will substitute domestic equipment and trim some higher-cost elements to bring the project within the city’s budget.

Staff also reported public-art activity: the public-art commission approved a community-designed mural for the Tustin Family Youth Center; the design will go to city council on April 7 for final approval, and community painting is planned for the third week of April under artist oversight. Separately, staff proposed a micro-gallery pilot (a locked display box for rotating student artwork) to be installed at the Columbus Tustin Recreation Center in partnership with Tustin Unified; an MOU with the school district is in development.

Commissioners and staff discussed dog-park turf conditions and potential annual closures (30–45 days) for overseeding or targeted turf replacement due to heavy use in the large-dog area. Staff said they considered artificial turf during design but public-works maintenance concerns led the department to retain natural turf at this time.