Keokuk council debates Grand Avenue reconstruction after engineers find full rebuild needed
Summary
Councilors reviewed a timeline showing core samples found asphalt too deteriorated for mill-and-fill, discussed engineering costs that rose when scope changed, and heard a low bid of $796,098.50 from Jones Contracting; some councillors favored moving ahead to avoid much higher future costs and others urged caution and better committee-to-council communication.
Get email alerts on the Infrastructure Streets topic
No spam. Unsubscribe anytime.
At a workshop immediately following a special meeting on April 27, 2025, the Keokuk City Council reviewed the Grand Avenue reconstruction timeline and debated whether to proceed after engineers determined a full reconstruction was necessary.
The chair presented a project timeline and said core samples taken in October 2024 showed the existing asphalt was “rotten,” so a mill-and-fill approach was no longer feasible and engineers were asked to prepare reconstruction plans. The presenter noted the city had paid $551,260 to the engineering firm and expected an additional engineering bill, increasing the total cost of professional services.
Councilors reviewed cost estimates. An earlier, rough opinion for a mill-and-fill had been around $300,000; after core sampling the engineer’s opinion ranged to $1.2–1.3 million for reconstruction. At bid opening on March 26 the council was told bids came in well under the engineer’s estimate; the transcript records Jones Contracting Corporation (West Point, Iowa) as the low bidder at $796,098.50.
Council debate split on timing and fiscal priorities. One council member urged accepting the low bid now, arguing that delaying would push the cost “up to 3 or $4,000,000” and that the current bid savings were partly because Jones was already mobilized in Keokuk on another project. That councilor emphasized that Grand Avenue north of Rand Park is heavily traveled and in dire condition and that doing the work now avoids much higher future costs.
Other councilors questioned the process that led to two engineering charges and recommended placing more structure on project sequencing so core samples and scope changes minimize duplicate engineering fees. One council member said approving separate engineering for mill-and-fill and later for reconstruction had resulted in approximately double engineering charges and that better communication between committees and council could reduce such costs in the future.
Two local contractors who bid on the project spoke: Dan Hickey (self-identified) said his company lost to Jones and praised Jones’ quality and competitive pricing; Jennifer Wilcox (self-identified), representing Jones Contracting, said the company’s presence in Keokuk for another project reduced mobilization costs and warned that rebidding later would likely increase the project price.
No final council vote to accept or reject the low bid appears in the workshop transcript. A council member formally requested the item be placed on the next feasible council agenda for potential reconsideration; staff said if a member who voted 'no' requests it, the item will appear on the May 15 council meeting agenda so absent members can participate in the decision.
What happens next: The project may be placed on the May 15 council agenda for reconsideration if requested by a council member who previously voted against moving forward; staff will provide additional documentation as requested.