Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Flagstaff previews transportation capital projects totaling hundreds of millions in planning and construction

City of Flagstaff Transportation Commission · April 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Capital improvements engineer Trevor Henry reviewed completed and upcoming projects including Beulah/University realignment (reported at $24 million), the John Wesley Powell extension (city portion ~ $49 million), Butler corridor projects, the Lonetree overpass and a Downtown Mile package; Henry said the JWP GMP will go to council April 21 and construction timelines run through 2028–2029 for major items.

Trevor Henry, the city’s capital improvements engineer, gave commissioners a multi-project update on the transportation capital improvement program, covering completed work, projects under construction and major upcoming investments.

Henry said the Beulah–University realignment is complete and "came in at 24,000,000," with construction costs near 21,000,000 and a mix of Proposition funds and developer contributions. He reviewed the Cedar/Locket 4th roundabout (an ADOT-administered project with a city share and an ADOT share) and then turned to larger projects…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans