District staff outline bid timeline and schedule constraints for Camas High fieldhouse/dome project
Summary
District construction consultants and staff presented a permit, bidding and construction timeline for a fieldhouse/dome project: targeted bid opening May 6, board award recommendation at the May 11 workshop, demolition/notice to proceed after May 13, resurfacing window critical for the boys’ season (must be done by Aug. 24), dome assembly around Oct. 23 and a forecasted finish near the December holiday break.
Randy, a district staff member, and consultant Dax presented a micro‑schedule and key procurement milestones for the Camas High fieldhouse and dome project. Consultants said permit review is in process and the district is targeting a bid opening on May 6, with an award recommendation to the board at the May 11 workshop if schedules and funding align.
Dax described coordination constraints among three contract streams (district general contract, USDA-supplied dome equipment and a dome subcontractor). The construction team said they must achieve a notice‑to‑proceed and begin demolition soon…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat