Board OKs $47,125 change order for Allen Water Treatment Plant design work

Englewood Water and Sewer Board · April 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Water and Sewer Board approved a $47,125 change order for EDOS to cover redesign and relocation work at the Allen Water Treatment Plant administration building after a critical underground water line was discovered; the change raises the contract authorization to $293,985.

Sarah presented a proposed change order to the contract with EDOS for design and services during construction at the Allen Water Treatment Plant administration building. She said a critical water line was discovered while investigating the planned foundation, which required relocation of the building and additional redesign work.

The board was asked to authorize a $47,125 change order to increase the contract total authorization to $293,985. Chair Moore moved the item and the board approved the change order by voice vote without recorded opposition.

Sarah said the change order is being brought early to secure the additional design work; staff reported the project remains within budget and that the additional authorization does not represent final spending to date.