Board approves up to $4.64 million contract for Wiley Elementary renovation

Dexter Community School District Board of Education · March 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board authorized award of Series 1 Bid Package 3 for Wiley Elementary with contract management assigned to Granger and a not‑to‑exceed amount of $4,640,346; the board and project team described remaining bid categories and an estimated total project cost near $5.6 million.

The Dexter Community School District Board of Education voted to award Series 1 Bid Package 3 for Wiley Elementary and to assign management of that package to Granger with a contract not to exceed $4,640,346, the chair reported during the March 18 meeting.

Board packet materials and presenters described the scope contained in Bid Package 3: demolition, site concrete, roofing, glazing, interior finishes (flooring, tile, painting), plumbing and piping, mechanical controls, electrical, and associated general trades. Presenters said the contract covers the majority of the addition and interior work; three categories (steel/security/resurfacing) had no suitable bidders at bid opening and remain pending.

A project representative, identified in the meeting as Greg, said most categories received competitive bids and that one bidder retracted a submission for clerical reasons; the district is working with the second bidder for that category. Project leads estimated remaining work at roughly $450,000 and an overall project estimate of about $5,600,000 once all packages are awarded.

Presenters explained construction sequencing and mitigation: heavy demolition and the masonry connection to the existing building (the noisiest items) will be scheduled to minimize impact on classrooms; foundation and utility work will begin in the summer, with fenced construction zones and temporary accessible paths to keep playground and bus loop operations functioning during the school year. Contract documents include calendar restrictions that limit disruptive work on testing or other sensitive school days, and the district said a superintendent-level project contact will be on site to address disruptions immediately.

Board members asked about displacement of playground equipment and logistics; presenters said playground use will be preserved and any resizing is limited, and the athletic field will remain full size though some outfield adjustments are possible.

The board approved the award by voice vote and directed staff to continue posting timelines and updates to the public‑facing project page.

Note on transcript spelling: the vendor/manager name appears in the packet and transcript with inconsistent spellings ("Granger" and "Grainger"). The district packet referenced in the meeting assigns management for this package; the board motion and packet language govern the award.