Anvil Telecom general manager Gina Parsons told the board the ARPA-funded Danville project will initially serve about 18 homes (underserved defined as <100/20 Mbps), with potential to expand; supervisors pressed on schedules, permits and contractor communication.
Get email alerts on the Broadband topic
No spam. Unsubscribe anytime.
Gina Parsons, who identified herself as general manager of Anvil Telecom, told the Des Moines County Board that Danville Telecom’s fiber project—partially funded by a $355,000 ARPA allocation—targets underserved locations (presented as areas with download speeds under 100 Mbps and upload speeds under 20 Mbps).
Parsons said the current plan maps to about 18 homes for the initial build but includes room for later expansion. She said the company aims to complete the funded scope before the 2026 ARPA deadline and that permits and construction will move quickly once started.
A supervisor raised concerns about past subcontractor performance on similar projects, citing communication and cleanup problems; Parsons said the company will ensure better subcontractor oversight and named Mike Baker as the project operations lead. County road staff offered to meet with any project consultants during their permit review to reduce permit-review time.
Supervisors asked for clarity on the service area map; Parsons said the locations are the same areas identified in the 2020 planning discussions and that the presentation here was a different format of the same footprint.
What’s next: Parsons invited questions and said she would provide updates as permits and construction milestones progress.