Vernon Hills to hire Leopardo as construction manager for police station renovation; staff warns GMP will return for approval
Summary
Trustees approved Resolution 2026-006 to waive formal bidding and execute a construction-manager-at-risk contract with Leopardo Construction for the police station project; staff said Leopardo’s preconstruction fee is $30,000, its fee 2.25% on subcontract packages and general-conditions estimates (24-month schedule) raise the total CM-related value to about $2.4 million.
The Village Board voted Feb. 17 to waive competitive bidding and authorize entering a construction-manager-at-risk agreement with Leopardo Construction for the police station addition and renovation project.
Director Bonata reviewed how the village selected the construction-manager (CM) delivery method and why CM-at-risk is appropriate for a complex, phased renovation that must keep existing operations functioning. He outlined the RFP and evaluation process: eight firms showed…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat