Staff unveils 90% design for Allen Park boat-trailer parking, estimates about $3.36 million
Summary
City engineering staff presented a 90% design to convert the former Public Works site into a 48-stall boat-trailer parking lot with gated access and on-site stormwater infiltration; staff said council review could occur in May or June 2026 and construction might begin in 2027 if funded and permitted.
Engineering specialist Jillian Longley presented the 90% design for a boat-trailer parking lot at the former Public Works site north of Bonney Lake Boulevard adjacent to the senior center and ball fields.
Longley said the project would create 48 trailer stalls protected by a perimeter fence and electric gate, repave the senior-center auxiliary parking, and manage stormwater on site with bioretention swales and planters to infiltrate runoff. "Primary public…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat