Grape Pond Phase 1 sewer: contracts awarded; Route 28 closure to begin April 1
Summary
DPW staff reported two contracts awarded for the Grape Pond Phase 1 sewer project, bids that cut estimated cost to about $53M, a state 0% loan covering roughly $41M of eligible work, and a temporary Route 28 closure April 1–May 22 for construction.
Amy Lowell, the town's water superintendent, gave a detailed update on the Grape Pond Phase 1 sewer project and associated construction impacts.
Lowell said the project was divided into two contracts: CC Construction (lift station and force mains) and RJV Construction (collection system). Together the low bids reduced the estimated project cost from about $60 million to about $53 million. The State confirmed a 0% interest loan for the eligible portion (about $41 million), and the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat