Summary
The board discussed extensive courthouse cupola repair needs, directed contractors to inspect and return with estimates to determine whether the work exceeds the $100,000 bidding threshold, and approved a Johnson Controls service agreement to be paid from the building fund.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Supervisors reviewed options for repair of the courthouse cupola and directed staff to obtain contractor inspections and additional quotes to determine whether the work would exceed the $100,000 threshold that requires formal bidding and architectural specifications.
Speakers described photographic and blueprint evidence suggesting the dome may not have been constructed to original specifications; Speaker 1 said there is documentation and pictures that "show that it wasn't built to spec" and recommended pursuing the original builder where appropriate. Speaker 5 (the county engineer) and others stressed that an architect or engineer may be needed and that costs to remove and reinstall the dome elements could be substantial.
The board agreed to invite a contractor (Randall/Rano) to inspect the dome this week, collect bids and bring estimates back for next-week consideration if available; if quotes show the project exceeds $100,000 the county will pursue formal bidding and plan/spec development.
Separately, the board approved a Johnson Controls service agreement to be paid from the building fund. The motion to fund the Johnson Controls repair from the building fund passed by roll call with supervisors voting aye. No dollar amount for the Johnson Controls work was stated on the record.
Supervisors also noted other building-maintenance items and the need to determine warranties, materials and manufacturer specifications before final contracting decisions were made.