Citizen Portal
Sign In

Lifetime Citizen Portal Access — AI Briefings, Alerts & Unlimited Follows

Parish says power plant rebuild will boost resilience; officials explain grid limits and local benefits

Terrebonne Parish President Town Hall · April 16, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Parish leaders described a 2–3 year project to demolish and rebuild the power plant, temporary generators providing 20 MW of capacity and plans to participate in regional grid systems; officials said local generation improves resilience though produced electricity will enter the broader MISO grid.

Parish officials outlined plans to demolish and rebuild the parish's power plant over a two- to three-year period, strengthen transmission infrastructure and pursue opportunities to sell electricity into regional markets while retaining resilience benefits for local customers.

The president said the power plant project was "a $170,000,000" obligation being processed with FEMA and noted the parish must meet local deductible and matching requirements. He said temporary generators currently provide about 20 megawatts of capacity while the new plant is constructed. On grid operations, the president explained that the parish is part of a Louisiana Economic Power Authority (LEPA) pocket and connected to MISO, the regional system operator, and that electricity produced locally participates in the broader grid even though local generation increases the parish's ability to sustain itself during outages.

When asked whether local residents would get the first benefit of locally produced electricity, the president said electrons move through the regional system but having local generation allows the parish to avoid rolling blackouts and potentially reduce the amount of power it must buy. He described upgrades such as a 115,000-volt transmission-line hardening program, a 50 MVA transformer for Plant Substation 2 and pilot meter/SCADA projects to improve outage detection and monitoring.

Officials did not provide a firm revenue projection for the plant but said estimates vary and depend on future power prices; earlier, the president referenced an illustrative $10 million figure but called it an estimate. The plant rebuild remains subject to FEMA funding timelines, local match obligations and multi-year construction planning.

Officials said they would continue technical discussions with LEPA, energy partners and MISO to determine costs, interconnection and how additional megawatts could be brought to the parish.