The commission tabled a request by Kelly Friese to legalize approximately 921 cubic yards of rubble fill at 1250 West Airline Highway after staff recommended denial and neighbors raised runoff and safety concerns; commissioners requested a staff/engineering site inspection and drainage analysis before the next meeting.
Get email alerts on the Land Use Permit topic
No spam. Unsubscribe anytime.
The Planning, Programming, and Zoning Commission voted to table consideration of a special permit to legalize about 921 cubic yards of rubble fill placed at 1250 West Airline Highway.
Staff recommended denial, citing that the property is primarily residential in use despite industrial zoning, the presence of a shared driveway, storage of vehicles and containers on site, and uncertainty about drainage and whether the fill was placed in the floodplain. Staff said a special permit is required for filling over 25 cubic yards and that the material had been deposited without prior approval. The applicant, Kelly Friese, said she had used clean demolition material from a city demo job as a stable base to store and access concession trailers, and that she stopped work after realizing a permit was required.
A neighboring property owner, Kelly White, told the commission she feared runoff and safety issues and asked the commission to decline the permit. VJ Engineering (Dan Aarons) told the commission he inspected the fill, said it mostly filled a low spot and did not appear to change drainage during his visit, and offered to coordinate further field review. Commissioners expressed divergent views and asked staff to coordinate an on-site review with engineering and return with a drainage analysis before taking a final vote. The commission then voted to table the item pending staff and engineering follow-up.
Why it matters: staff reported the site contains a substantial unauthorized fill (about 921 cubic yards), raising permitting, floodplain, drainage and neighbor-safety concerns; tabling preserves the council’s ability to require removal or remediation depending on technical findings.
Next steps: staff and engineering will inspect the site, report back to the commission with drainage findings and recommended conditions or remediation options before the item returns for decision.