Chisago County details Highway 8 study, warns of wetlands mitigation and 2027–29 construction window
Summary
Chisago County Public Works Director Joe Triplett told the Wyoming City Council the Highway 8 study is examining roundabout and realignment options, that environmental review shows over 20 acres of wetland impacts needing costly mitigation, and that construction is tentatively targeted for 2027–2029.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Chisago County Public Works Director Joe Triplett told the Wyoming City Council on July 15 that the county is studying several alternatives for the Highway 8/Casa 22 area, including roundabouts and a possible realignment of Kettle River Boulevard to serve a proposed development.
Those alternatives are still in early modeling, Triplett said. He added the Trunk Highway portion of the project would be handled by MnDOT and would require outside funding; “if they indeed want that, they’ll have to bring funding to the table,” he said.
The study is also in environmental review. Triplett said the county has identified “over 20 some acres of wetland impacts” that will require sizable, and likely expensive, mitigation work. He said the county has sought authorization to begin right-of-way buyouts and relocations ahead of final environmental clearance to give staff more time to work with affected residents.
“Right now, it’s looking like a ’27, ’28, and ’29 construction” window, Triplett said. He warned that ongoing price increases mean the county will need additional fundraising and said the county’s goal is to limit or eliminate direct city or county financial participation in the trunk-highway portion of the work.
On funding, Triplett said the project is being pursued through many sources but that at least one federal pot was put on hold. He said a Stauber-designated CDS allocation was pulled and that the county has applied for $8,000,000 in congressionally directed spending; he said that request "made it through Stobbers, made it through Klobuchar," and added, "so, again, we're hopeful," while acknowledging uncertainty about timing and final authorization.
A council member asked whether federal funding had been cut; Triplett said some funds are on hold and the county does not yet know whether or when specific allocations will be restored.
The county estimates the right-of-way effort could affect between roughly 240 and 300 parcels, a scale Triplett described as “a heavy lift.” He said the next six months should produce 90% plans, clearer environmental clearance, and a better sense of right-of-way impacts.
The county’s study and funding decisions will determine what transportation improvements are feasible and when construction might proceed.