Needles details roughly $15 million in water upgrades funded by state grant

City Council, City of Needles · April 18, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Development Services Director Kathy Rasch told the council the city used a 2020 State Water Resources Control Board construction grant (with subsequent amendments) to complete six major water projects — including a new Well‑11 treatment plant and two booster stations — totaling about $14.3 million in grant funds and roughly $15 million including related work and reimbursements.

Development Services Director Kathy Rasch told the City Council on April 14 that Needles has completed the majority of water capital work funded through a 2020 drinking‑water construction grant from the California State Water Resources Control Board and subsequent amendments.

Rasch said the grant and later amendments supplied about $14.3 million for six projects. Major items Rasch listed included an L Street water booster station (about $897,814), the Lily Hill booster station (about $2.2 million), a Well‑11 centralized treatment facility (reported at about $6.0–6.3 million), a transmission line connecting Well 11 to Well 15 (about $970,000), and a Well 15 backup generator (about $375,000). Staff also reported manifold and distribution work on Monterey and River Road (estimated at about $1.5 million). Rasch said soft‑cost reimbursements (engineering, construction management, testing and signage) are roughly $500,000 and water‑service replacements associated with paving projects total about $2.4 million, which together bring expenditures to around $15,000,000 to date.

"In 2020, the city received a drinking water construction grant from the California State Water Resources Control Board and subsequent amendments over four amendments for a total of $14,300,000 in funding for six projects," Rasch said during her presentation, summarizing the large projects and their purposes, including continuous removal of iron and manganese at the Well‑11 treatment site.

Council members thanked staff for securing external funding and completing the work with minimal service interruptions. Rasch said nearly all grant‑funded work is complete except for a manifold component that is expected to finish in about 30 days; staff will prepare the final report to the state when work is complete.

Why it matters: the upgrades create new treatment capacity and increase distribution reliability without a general‑fund capital outlay for the utility; staff said the work reduces operational vulnerability and positions the city to meet drinking‑water standards.

Next steps: staff will finish the remaining manifold work, file final reports required by the state grant, and return on any substantive outstanding implementation items when required.