Commissioners reviewed a plan to acquire navigation easements (perpetual rights to control trees in approach surfaces), discussed appraisal and survey requirements and a ballpark $630,000 two‑year estimate; the state offered to fund 100% of a vegetation management study and a MassDOT scoping meeting was scheduled.
Get email alerts on the Land Use Easements topic
No spam. Unsubscribe anytime.
The Gardner City Airport Commission reviewed plans to acquire navigation (airspace) easements and a vegetation‑management study that the state will fund in full.
Presenter explained that acquiring easements means property owners keep use of the ground, but the airport would obtain perpetual rights to trim or remove trees in impacted airspace. Federal regulations require a property boundary survey, an appraisal and an independent review of the appraisal; payments to owners must reflect fair market value. Presenter said these steps are intended to protect property owners and ensure fair compensation.
Commissioners discussed preliminary cost expectations. One participant summarized the rough estimate as about $630,000 to accomplish easement acquisitions and related work over two years, but Presenter cautioned this is a ballpark figure because fees for subconsultants (appraisers, review appraisers and surveyors) are not yet developed. Presenter said staff will prepare a draft scope of services (Gale Associates is under contract for related work) and then the scope, independent fee estimate and final contract fee will return to the commission for approval.
Presenter also described a vegetation management plan that the Massachusetts Aeronautics office has offered to fund 100%: the study will analyze the airport's airspace (approaches, primary/transitional/horizontal/conical surfaces), identify wetlands and habitat concerns, and produce a five‑year operational plan to guide what the airport can clear with in‑house equipment versus what needs contracting. Presenter said a scoping meeting with MassDOT is scheduled and the study will be coordinated with FAA and MassDOT before coming back to the commission.
Presenter said no formal acquisition action was required at the meeting; staff will finalize the scope, obtain cost estimates and return recommended contract(s) for commission review and approval.
Clarifying detail cited in the meeting: Presenter referred to "a little bit over $25,000" in a cost table without specifying the line item; staff will clarify cost breakdowns when the scope and fee estimates are developed.