Lifetime Citizen Portal Access — AI Briefings, Alerts & Unlimited Follows
Board hears update on school capital projects, Forest Hills pre‑construction scheduled
Loading...
Summary
The board received a facilities update covering Arnett Hills opening, Langston renovation, Glenwood skilled‑trades center, and plans for Forest Hills funded by the 1% sales tax plus an $8.5 million grant; pre‑construction and swing‑space logistics were described.
A district facilities presenter reviewed progress and next steps for several capital projects across the district. The board was told Arnett Hills is opening and Langston work continues as a renovation; GW High School’s CTE spaces and the Glenwood skilled‑trades center are in progress.
For Forest Hills Elementary, the presenter said funding will combine the 1% sales tax and an $8,500,000 grant and described a condensed pre‑construction timeline that keeps students in place while early work proceeds. The district plans to move the Conway House (an acquired home) and repurpose it at the GW campus to provide swing‑space for special‑education life‑skills programming. Staff described an RFP to move the house and plans for clearing classrooms with teacher and grade‑level participation in the packing process.
The presenter listed additional projects — roofing needs at Bonner, interior upgrades at Park Avenue and Glenwood, restroom upgrades and parking work — and noted some projects lack firm timelines. The board also heard that an elevator addition at Glenwood could be completed by January 2027 rather than 2028 if scheduling allows.
Board members asked about public access to the History Hub at GLH/Johnson and how the community can arrange visits; staff said visitors may check in through main offices and that some areas require escorting. The presenter noted a dip in sales tax receipts earlier in the year but said the latest report returned to previous levels.
No formal vote was taken on capital projects during the update.

